Scope of Work
- Design and Construct Project.
- RORO.
- Sheetpiling.
- Light Vessel Jetty.
- Barge/Boat Ramp.
- MOF Crane Pad.
- Cyclone Moorings.
- Pavement.
Pacific Marine Group were awarded the Abbot Point Maintenance and Offloading Facility by NQBP in August 2016.
Pacific Marine Group was responsible for:
- Earthworks and rock armouring.
- Concrete works.
- Over 1000 tons of concrete used on site including:
- 72 precast planks for the barge ramp.
- 27 concrete blocks to tie back the new sheet pile walls.
- Roll On Roll Off (RORO) Ramp.
- Capping Beam.
- Crest wall.
- Barge ramp.
- Light Vessel Jetty.
- Rock Armouring.
- Almost 5000 tons of rock armouring used to protect the new facility.
- Largest rocks weighed approximately 8 tons and were 1.8m high each.
- Sheetpiling.
- Over 100m of sheet piles walled installed by Pacific Marine Group.
- 72 sheet piles installed up to 18m in length driven up to 11.5m below seabed.
- 190 ton of sheetpiles used.
- Just over 1.1km overall length.
- Installed with Pacific Marine Group 180 foot barge, 100 ton crane and driving hammers.
							Get In Touch
							
						11-15 Sandspit Drive
 South Townsville 4810,
 Queensland, Australia
P. +61 7 4724 2200
 F. +61 7 4724 2208
							Services
							
						
						
							Company
							
						
					 
                     
                     
                     
                     
                     
                     
                     
                     
							 
							 
							 
							 
							