Scope of Work
- Design and Construct Project.
- RORO.
- Sheetpiling.
- Light Vessel Jetty.
- Barge/Boat Ramp.
- MOF Crane Pad.
- Cyclone Moorings.
- Pavement.
Pacific Marine Group were awarded the Abbot Point Maintenance and Offloading Facility by NQBP in August 2016.
Pacific Marine Group was responsible for:
- Earthworks and rock armouring.
- Concrete works.
- Over 1000 tons of concrete used on site including:
- 72 precast planks for the barge ramp.
- 27 concrete blocks to tie back the new sheet pile walls.
- Roll On Roll Off (RORO) Ramp.
- Capping Beam.
- Crest wall.
- Barge ramp.
- Light Vessel Jetty.
- Rock Armouring.
- Almost 5000 tons of rock armouring used to protect the new facility.
- Largest rocks weighed approximately 8 tons and were 1.8m high each.
- Sheetpiling.
- Over 100m of sheet piles walled installed by Pacific Marine Group.
- 72 sheet piles installed up to 18m in length driven up to 11.5m below seabed.
- 190 ton of sheetpiles used.
- Just over 1.1km overall length.
- Installed with Pacific Marine Group 180 foot barge, 100 ton crane and driving hammers.
Get In Touch
11-15 Sandspit Drive
South Townsville 4810,
Queensland, Australia
P. +61 7 4724 2200
F. +61 7 4724 2208
Services
Company