Client

BHP Billiton Mitsubishi Alliance

Time

2018

Contract Value

$236,000

Download Case Study
Back to List

Scope of Work

Assessment of the concrete caisson AC4 to determine the internal structural condition of the pre tensioned strand wires.

Diving Tasks:
  • Identification of the cutting areas on the caisson concrete surface.
  • Cut the concrete windows to expose the strand wire conduits using precision cutting technology.
  • Cut a window on the metal conduits.
  • Remove the filling concrete around the strand wires by hydro blasting.
  • Expose the strand wires and inspect for structural integrity.
  • Cut samples of the strand wires for laboratory analysis.
  • Inspect the sour mattresses around the caisson to determine the overall condition (Berth 2 northern caisson and MC3).